checklist for arrow diagrams
- provide a legend that shows location of:
- activity name
- activity duration
- early event time
- late event time
- activity total float
- neatly draw each activity arrow from left to right
- there should be one single starting node
- there should be a single ending node
- include nodes for project milestones
- except when joining at i- or j- nodes, arrows should be parallel
- all nodes should be numbered
- node numbers should always positive integers, and J-node > I-node
- skip 5 between each node number
- redraw the diagram, as needed, to eliminate crossed activity arrows
- use logic and numbering dummies when needed
- after calculating the network clearly identify the critical path